|
28
July 2008
Hindalco
announces Q1 FY 2008-2009 results
Click
here to view the results
| Revenues |
Rs.
4,648 crore
|
| PBITDA |
Rs.
1,164 crore
|
| PAT |
Rs.
697 crore
|
Financial
highlights
| (In
Rs. crore) |
Quarter
ended 30 June 2008
|
Quarter
ended 30 June 2007
|
| Net
sales and operating revenue |
4,647.5
|
4,685.2
|
| Other
income |
214.7
|
124.6
|
| Profit
before depreciation, interest and tax |
1163.7
|
1,005.7
|
| Depreciation
|
156.8
|
143.7
|
| Interest
and finance charges |
76.1
|
56.3
|
| Profit
before tax |
930.8
|
805.7
|
| Provision
for taxes |
234.0
|
207.1
|
| Net
profit |
696.8
|
598.6
|
| Basic
EPS |
5.68
|
5.42
|
Hindalco
Industries Ltd. announced its unaudited financial results
for the quarter ended 30 June 2008.
Net sales and operating revenues remained flat at Rs. 4647.5
crore, however the profit before depreciation, interest and
tax grew by 16 per cent to Rs. 1,163.7 crore as compared to
Rs. 1,005.7 crore in the corresponding period in FY 08. The
profit after tax at Rs. 696.8 crore was up 16 per cent from
Rs. 598.6 crore in Q1 FY08.
Of the total revenues of Rs. 4647.5 crore, aluminium business
contributed Rs. 1943.0 crore. The profit before interest and
tax for aluminium business was higher by 18 per cent from
Rs. 638.2 crore to Rs. 750.4 crore in the corresponding quarter
of the preceding year, driven by higher volumes and higher
LME prices.
In the copper business, revenues were lower at Rs. 2706.6
crore against Rs. 2926.2 crore mainly on account of lower
volumes due to a planned shutdown of smelter-1 at Dahej.
The steep depreciation of the Indian Rupee against the US
Dollar affected the copper business by an estimated Rs. 151.9
crore for the quarter under review, as a result of restatement
of net foreign currency exposures as on 30 June 2008. For
the corresponding quarter of the previous year, this had an
estimated favourable impact of Rs. 14.3 crore. Consequently,
the PBIT of copper business is lower than the corresponding
quarter of the previous year by Rs.166.2 crore.
The profit before interest and tax was lower at Rs. 74.3 crore
from Rs. 112.3 crore in the corresponding quarter last year.
Operational review
Aluminium
The expansion at Muri and Hirakud has resulted in alumina
production going up by 31 per cent at Muri and metal production
by 24 per cent at Hirakud. The overall metal production was
up by 7 per cent. The value added wire rods production was
also up by 4 per cent.
At Mouda, production was lower due to stoppage of cold rolling
mill.
Extrusions production rose by 8 per cent on back of the investments
made in new presses in the last two years.
| Production |
Units
|
Quarter
ended 30 June 08
|
Quarter
ended 30 June 07
|
| Alumina |
MT |
303,477
|
302,430
|
| Primary metal |
MT |
123,885
|
116,169
|
| Wire
rods |
MT |
18,149
|
17,433
|
| Rolled products |
MT |
51,334
|
53,868
|
| Extruded
products |
MT |
11,019
|
10,185
|
| Foils |
MT |
7,283
|
7,397
|
| Wheels |
Nos. |
46,992
|
44,576
|
| Power |
MT |
2,221
|
2,164
|
Copper
Copper cathodes production is lower due to the planned shutdown
of smelter-1 in this quarter. The copper smelter II
operations continue to be suspended.
Cathode production reduced by 24 per cent to 60 kt. To maximize
production of value added products, continuous cast rods production
was curtailed only by 12 per cent to 30 kt.
| Production |
Units
|
Quarter
ended 30 June 08
|
Quarter
ended 30 June 07
|
| Copper
cathodes |
MT |
60,434
|
79,234
|
| Continuous cast
copper rods |
MT |
30,165
|
34,094
|
Expansion
projects
Muri
The expansion of the Muri alumina refinery from 110,000 tpa
to 450,000 tpa is mechanically complete. Production is being
ramped up in a phased manner. The entire steam and power requirement
is being met by the new captive power plant. The production
from the expanded facility is proposed to reach its full capacity
by the end of the year.
Hirakud
Phase II of the expansion of the smelting capacity from 100,000
tpa to 143,000 tpa is on schedule. Its capacity has touched
122,000 tpa in this quarter and is expected to scale upto
143,000 tpa by August 2008. The power generation capacity
has been raised from 267.5 mw to 367.5 mw. All the units have
been commissioned.
Belgaum
The allotment of the lease for bauxite mines for expanding
the alumina refinery capacity at Belgaum, Karnataka from 350
ktpa to 650 ktpa is still awaited.
Aditya Aluminium Project
Aditya Aluminium, the integrated aluminium project, encompassing
1 to 1.5 million tpa alumina refinery, 260,000 to 359,000
tpa aluminium smelter and 750 to 900 mw captive power plant
is progressing as planned. A major portion of the total land
required for the project has been acquired. Environmental
clearances have been obtained for the smelter, the captive
power plant (CPP) and the alumina refinery. The water drawl
agreement has also been executed. The construction power is
already in place. The construction of transmission lines and
upgradation of substations to draw power is in progress. The
first metal from the smelter is proposed to be produced by
October 2011. The refinery is proposed to be mechanically
completed by January 2013. The technology contracts for the
smelter and alumina have been executed with Aluminium Pechiney
and Alcan respectively. The basic engineering activities for
the smelter and CPP have commenced.
Mahan project
The Mahan aluminium project with a smelter capacity of 359
ktpa and CPP of 900 mw is on track. The land acquisition for
the project is underway. The company has been allotted a coal
block in a JV with the Essar group for the coal requirement
of the CPP. Preliminary environmental clearances have been
obtained. The power connectivity for commencing construction
has been approved. The water resource department has provided
the necessary facilities as well. The production of coal is
expected to start by October 2009. The technology contract
for the smelter has already been executed with Aluminium Pechiney.
The first metal from the smelter is expected by July 2011
and basic engineering activities for the smelter and CPP have
begun.
Jharkhand
project
The proposed smelter capacity of the Jharkhand aluminium project
is 359 ktpa and a CPP of 900 mw. The plant location is being
shifted from Latehar to Sonahatu block which is 20 kilometers
from Muri and 55 kilometers from Ranchi. The company is preparing
to submit the application for the government land. The government
of Jharkhand has given the water allocation clearance for
55 mcm of water from Subernrekha basin. Tubed coal mine has
been allotted jointly with Tata Power. The technology contract
for the smelter has already been executed with Aluminium Pechiney.
The approximate date for the first metal from the smelter
is expected by June 2012.
Utkal
The construction of Utkal alumina refinery with a proposed
capacity of 1.5 mtpa is currently underway. The company has
acquired the land for the plant and other facilities. The
basic engineering packages have already been received from
Alcan (technology supplier). Major packages have been ordered.
The detailed engineering for the main plant area is nearing
completion. The civil works for alumina refinery and captive
power plant is in progress. Bauxite mining activities is expected
to start by mid 2009. The mechanical completion of the plant
is expected by January 2011 and the first alumina is expected
to be produced around July 2011.
Hindalco Almex Aerospace Limited
This joint venture company for the manufacture of high-strength
aluminium alloys for applications in the aerospace, sporting
goods and surface transport industries is at an advanced stage
of implementation. Key equipments have arrived at the site
and are under installation. The project is proposed to be
completed by end of August 2008.
This press release does
not constitute or form part of any offer or invitation to
sell or issue, or any solicitation of any offer to purchase
or subscribe for, any equity shares, not shall it or any part
of it, nor the fact of its distribution from the basis of,
or be relied on in connection with, any contract or investment
decision.
This press release is not for publication or distribution
to persons in the United States, and is not an offer for sale
within the United States of any equity shares or any other
security of the Company. Securities of the Company, including
its equity shares, may not be offered or sold in the United
States absent registration under U.S. securities laws or unless
exempt from registration under such laws.
|