|
28 July 2008
Hindalco announces Q1 FY 2008-2009 results
Click
here to view the results
| Revenues |
Rs.
4,648 crore
|
| PBITDA |
Rs.
1,164 crore
|
| PAT |
Rs.
697 crore
|
Financial highlights
| (In
Rs. crore) |
Quarter
ended 30 June 2008
|
Quarter
ended 30 June 2007
|
| Net
sales and operating revenue |
4,647.5
|
4,685.2
|
| Other
income |
214.7
|
124.6
|
| Profit
before depreciation, interest and tax |
1163.7
|
1,005.7
|
| Depreciation
|
156.8
|
143.7
|
| Interest
and finance charges |
76.1
|
56.3
|
| Profit
before tax |
930.8
|
805.7
|
| Provision
for taxes |
234.0
|
207.1
|
| Net
profit |
696.8
|
598.6
|
| Basic
EPS |
5.68
|
5.42
|
Hindalco Industries Ltd. announced its unaudited
financial results for the quarter ended 30 June
2008.
Net sales and operating revenues remained flat
at Rs. 4647.5 crore, however the profit before
depreciation, interest and tax grew by 16 per
cent to Rs. 1,163.7 crore as compared to Rs. 1,005.7
crore in the corresponding period in FY 08. The
profit after tax at Rs. 696.8 crore was up 16
per cent from Rs. 598.6 crore in Q1 FY08.
Of the total revenues of Rs. 4647.5 crore, aluminium
business contributed Rs. 1943.0 crore. The profit
before interest and tax for aluminium business
was higher by 18 per cent from Rs. 638.2 crore
to Rs. 750.4 crore in the corresponding quarter
of the preceding year, driven by higher volumes
and higher LME prices.
In the copper business, revenues were lower at
Rs. 2706.6 crore against Rs. 2926.2 crore mainly
on account of lower volumes due to a planned shutdown
of smelter-1 at Dahej.
The steep depreciation of the Indian Rupee against
the US Dollar affected the copper business by
an estimated Rs. 151.9 crore for the quarter under
review, as a result of restatement of net foreign
currency exposures as on 30 June 2008. For the
corresponding quarter of the previous year, this
had an estimated favourable impact of Rs. 14.3
crore. Consequently, the PBIT of copper business
is lower than the corresponding quarter of the
previous year by Rs.166.2 crore.
The profit before interest and tax was lower
at Rs. 74.3 crore from Rs. 112.3 crore in the
corresponding quarter last year.
Operational review
Aluminium
The expansion at Muri and Hirakud has resulted
in alumina production going up by 31 per cent
at Muri and metal production by 24 per cent at
Hirakud. The overall metal production was up by
7 per cent. The value added wire rods production
was also up by 4 per cent.
At Mouda, production was lower due to stoppage
of cold rolling mill.
Extrusions production rose by 8 per cent on back
of the investments made in new presses in the
last two years.
| Production |
Units
|
Quarter
ended 30 June 08
|
Quarter
ended 30 June 07
|
| Alumina |
MT |
303,477
|
302,430
|
| Primary
metal |
MT |
123,885
|
116,169
|
| Wire
rods |
MT |
18,149
|
17,433
|
| Rolled
products |
MT |
51,334
|
53,868
|
| Extruded
products |
MT |
11,019
|
10,185
|
| Foils |
MT |
7,283
|
7,397
|
| Wheels |
Nos. |
46,992
|
44,576
|
| Power |
MT |
2,221
|
2,164
|
Copper
Copper cathodes production is lower due to the
planned shutdown of smelter-1 in this quarter.
The copper smelter II operations continue
to be suspended.
Cathode production reduced by 24 per cent to
60 kt. To maximize production of value added products,
continuous cast rods production was curtailed
only by 12 per cent to 30 kt.
Production Units Quarter ended 30 June 08 Quarter
ended 30 June 07
Copper cathodes MT 60,434 79,234
Continuous cast copper rods MT 30,165 34,094
Expansion projects
Muri
The expansion of the Muri alumina refinery from
110,000 tpa to 450,000 tpa is mechanically complete.
Production is being ramped up in a phased manner.
The entire steam and power requirement is being
met by the new captive power plant. The production
from the expanded facility is proposed to reach
its full capacity by the end of the year.
Hirakud
Phase II of the expansion of the smelting capacity
from 100,000 tpa to 143,000 tpa is on schedule.
Its capacity has touched 122,000 tpa in this quarter
and is expected to scale upto 143,000 tpa by August
2008. The power generation capacity has been raised
from 267.5 mw to 367.5 mw. All the units have
been commissioned.
Belgaum
The allotment of the lease for bauxite mines for
expanding the alumina refinery capacity at Belgaum,
Karnataka from 350 ktpa to 650 ktpa is still awaited.
Aditya Aluminium Project
Aditya Aluminium, the integrated aluminium project,
encompassing 1 to 1.5 million tpa alumina refinery,
260,000 to 359,000 tpa aluminium smelter and 750
to 900 mw captive power plant is progressing as
planned. A major portion of the total land required
for the project has been acquired. Environmental
clearances have been obtained for the smelter,
the captive power plant (CPP) and the alumina
refinery. The water drawl agreement has also been
executed. The construction power is already in
place. The construction of transmission lines
and upgradation of substations to draw power is
in progress. The first metal from the smelter
is proposed to be produced by October 2011. The
refinery is proposed to be mechanically completed
by January 2013. The technology contracts for
the smelter and alumina have been executed with
Aluminium Pechiney and Alcan respectively. The
basic engineering activities for the smelter and
CPP have commenced.
Mahan project
The Mahan aluminium project with a smelter capacity
of 359 ktpa and CPP of 900 mw is on track. The
land acquisition for the project is underway.
The company has been allotted a coal block in
a JV with the Essar group for the coal requirement
of the CPP. Preliminary environmental clearances
have been obtained. The power connectivity for
commencing construction has been approved. The
water resource department has provided the necessary
facilities as well. The production of coal is
expected to start by October 2009. The technology
contract for the smelter has already been executed
with Aluminium Pechiney. The first metal from
the smelter is expected by July 2011 and basic
engineering activities for the smelter and CPP
have begun.
Jharkhand project
The proposed smelter capacity of the Jharkhand
aluminium project is 359 ktpa and a CPP of 900
mw. The plant location is being shifted from Latehar
to Sonahatu block which is 20 kilometers from
Muri and 55 kilometers from Ranchi. The company
is preparing to submit the application for the
government land. The government of Jharkhand has
given the water allocation clearance for 55 mcm
of water from Subernrekha basin. Tubed coal mine
has been allotted jointly with Tata Power. The
technology contract for the smelter has already
been executed with Aluminium Pechiney. The approximate
date for the first metal from the smelter is expected
by June 2012.
Utkal
The construction of Utkal alumina refinery with
a proposed capacity of 1.5 mtpa is currently underway.
The company has acquired the land for the plant
and other facilities. The basic engineering packages
have already been received from Alcan (technology
supplier). Major packages have been ordered. The
detailed engineering for the main plant area is
nearing completion. The civil works for alumina
refinery and captive power plant is in progress.
Bauxite mining activities is expected to start
by mid 2009. The mechanical completion of the
plant is expected by January 2011 and the first
alumina is expected to be produced around July
2011.
Hindalco Almex Aerospace Limited
This joint venture company for the manufacture
of high-strength aluminium alloys for applications
in the aerospace, sporting goods and surface transport
industries is at an advanced stage of implementation.
Key equipments have arrived at the site and are
under installation. The project is proposed to
be completed by end of August 2008.
This press release does not constitute or form
part of any offer or invitation to sell or issue,
or any solicitation of any offer to purchase or
subscribe for, any equity shares, not shall it
or any part of it, nor the fact of its distribution
from the basis of, or be relied on in connection
with, any contract or investment decision.
This press release is not for publication or
distribution to persons in the United States,
and is not an offer for sale within the United
States of any equity shares or any other security
of the Company. Securities of the Company, including
its equity shares, may not be offered or sold
in the United States absent registration under
U.S. securities laws or unless exempt from registration
under such laws.
For more information, contact:
Dr. Pragnya Ram,
Group Executive President,
Corporate Communications,
Aditya Birla Management Corporation Private Limited
Tel: 91-22-6652 5000 / 2499 5000
Fax: 91-22-6652 5741/ 42
Email: pragnya.ram@adityabirla.com
|