At Hindalco, we value quality, safety, and environmental consciousness and implement the same in all our projects.

Site work on all the greenfield projects has gained momentum and are in various stages of progress.

Corporate Projects and Procurement Cell, Mumbai
The Corporate Projects and Procurement Cell is the central and nodal cell for the evaluation, monitoring, control and implementation of all greenfield expansion projects and for procurement of major raw materials for all units of Hindalco.

Head: Mr. R. Ram

Greenfield expansion projects
include:

Madhya Pradesh: Mahan Aluminium Project
Click for larger view

Madhya Pradesh: Mahan Aluminium Project
The Mahan Aluminium Project is a smelter-power plant complex that boasts of a 359-ktpa aluminum smelter and a 900-MW captive thermal power plant.

The project has access to the Mahan coal block (off the main basin in the Singrauli coal fields) through a joint venture with Essar Power. Hindalco’s share in the coal block is about 3.6 million mtpa.

Site work has already started and is in full swing. Engineering and ordering of packages for both smelter and power plant are moving ahead of schedule. All the major approvals are in place and site activities are progressing well. Major contractors have mobilised at site. A major chunk of land is already acquired. The first metal from the smelter is proposed to be produced by Q2 FY12.

Project head, smelter: Mr. Apurba Musib
Project head, power plant: Mr. D. Bangabash


The Aditya Alumina and Aluminium Project is an INR 130 billion greenfield integrated aluminium complexOrissa: Aditya Alumina and Aluminium Project
Aditya Alumina and Aluminium Project is a greenfield integrated aluminium complex. The project includes a 4.2 million-tpa bauxite mine, 1.5 million-tpa alumina refinery at Kansariguda and 359-ktpa smelter at Lapanga. The refinery is expected to produce 2 million tpa within three years of its startup.

Orissa: Aditya Alumina and Aluminium Project
Click for larger view

The project also has a 20 million-tpa joint venture coal mine at Ib Valley, coal blocks Talabira II and III, Orissa, and a 900-MW captive power plant at Lapanga.

A major portion of the total land required for the project has been acquired. Most of the important clearances have been obtained, and major orders have been placed for the smelter and power plant.

The first metal from the smelter is proposed to be produced by Q3 FY12. The refinery is proposed to be mechanically completed by Q1 FY14.

Project head: Mr. S. Bontha


The Utkal Alumina Project has a 1.5 million-tpa alumina refinery at Doragurha in Raygada district Orissa: Utkal Alumina Project
The Utkal Alumina Project (Utkal Alumina) is a greenfield project, a wholly owned subsidiary of Hindalco.

Construction of 1.5 million-tpa alumina refinery at Rayagada, Orissa is in full swing. Over 85 per cent of the project cost has already been committed. Land and all statutory clearances required for the project have been obtained. Engineering for the project is nearing completion.

Orissa: Utkal Alumina International Limited
Click for larger view

Site work is going on in full swing with large contractors like L & T , Gannon Dunkerley and others, and major equipment like boilers, evaporators, turbines have started arriving at site. All the major orders have been placed.


The first alumina is expected to be produced around Q2 FY12.

Project head:
Mr. Surya Kant Mishra

Jharkhand: Jharkhand Aluminium Project
Click for larger view

Jharkhand: Jharkhand Aluminium Project
Located at Sonahatu, fifty-five kilometers from Ranchi, Jharkhand Aluminium project is a smelter–power plant complex with a capacity of 359 ktpa powered by a 900-MW captive thermal power plant.

In a joint venture, with Tata Power, we own a Coal Mine (Tubed) in the Auranga coal fields at Jharkhand. The coal mine has a capacity of 6 million tpa.

Land acquisition process has already commenced. Activities for getting the environmental clearance have also started. Water allocation clearance for 55 mcm of water from the Subarnarekha basin has been obtained. Technology agreement with Pechiney has also been inked for the aluminium smelter.

The first metal from the smelter is proposed to be produced by Q1 FY14.

To contact projects, click here

Back to top



 
   
 
 
 
   
 
  Sultan Salahuddin Abdul
Aziz Shah Mosque in the
state of Selangor in Malaysia has a dark blue aluminium dome that dominates the skyline of the state's capital, Shah Alam. The mosque is
one of the most beautiful buildings in Malaysia.